Reporting Timeline for Projects Funded in FY2025

Date Milestone
November 2024 Funds Available
April 15, 2025 1st Quarterly Report Due Date
July 15, 2025 2nd Quarterly Report Due Date
October 15, 2025 3rd Quarterly Report Due Date
December 31, 2025 Expected Project End Date (A single 6-month, no-cost extension may be granted if needed)
February  28, 2025 Final Report Due Date (Unless extension granted)

For projects funded in previous fiscal years, please continue submitting quarterly reports using the forms below until completed.

Submit Your Reports

Progress Report Submission

Submit Progress Report

Final Report Submission

Submit Final Report

Frequently Asked Questions

  1. How do I request a scope change?

    To request a scope change, you will need to create a revised budget sheet that includes the original line items and amounts but adds a new column with the proposed changes. The total amount spend cannot exceed the initial total approved. That document should be saved as "SCG Scope Change_Project Name" and submitted via email to shane.tedder@uky.edu along with a brief written justification.

  2. How do I request a no-cost, one-time extension?

    Please email a brief written justification to shane.tedder@uky.edu.